In accordance with the technical decision of ZNPP, in August 2016, the trial commissioning of the instrumentation and control system of the automatic regulating system of turbine division (I&C of ASR TO) took place at Unit 2.
This was preceded by the following:
- receipt of permission for building and assembly;
- dismantlement of the ASUT-1000М equipment, excepting the turbine regulating system, and installation of the equipment of I&C of ASR TO at Unit 2;
- autonomous checks of ASR TO;
- complex adjustment and test of ASR, protections and interlockings;
- metrological certification of measuring channels I&C of ASR TO;
- introduction of changes into maintenance documentation;
- training of personnel involved into operation of I&C of ASR TO, knowledge assessment;
- development of a trial operation program for I&C of ASR TO at Unit 2.