ENG
19.04.2023

(RU) ПРОВЕДЕНЫ ПРИЕМОЧНЫЕ ИСПЫТАНИЯ ПРОГРАММНО-ТЕХНИЧЕСКИХ СРЕДСТВ ДЛЯ МОДЕРНИЗАЦИИ МСКУ-4 ИЗ СОСТАВА ПТК КИП СНЭ РО

19.04.2023

ACCEPTANCE TESTS OF SOFTWARE AND HARDWARE TOOLS FOR MODERNIZATION MSKU-4 FROM OF SOFTWARE AND HARDWARE COMPLEX OF CONTROL AND MEASURING DEVICES OF THE NORMAL OPERATION SYSTEM FOR THE REACTOR DIVISION (SHC of CMD of NOS RD) HAVE BEEN CARRIED OUT

05.04.2023

HANDOVER-ACCEPTANCE TESTING OF TECHNICAL FACILITIES FOR MODIFICATION OF AKNP-IF RNPP-4 HAVE BEEN CARRIED OUT

30.03.2023

PILOT OPERATION OF AXLE COUNTING EQUIPMENT IS COMPLETED AT “STEPOK-STANISHEVKA” AND “VASYLKOV-1 – VASYLKOV-CENTER” SPANS

28.03.2023

20 COMPLEXES FOR MONITORING THE TECHNICAL CONDITION OF AKRO-B ROLLING STOCK ARE INSTALLED AT THE FACILITIES OF JSC «UKRAINIAN RAILWAYS»

18.02.2023

HANDOVER-ACCEPTANCE TESTING OF REGISTRATION AND DISPLAY DEVICES FOR OF SUNPP HAVE BEEN CARRIED OUT

30.01.2023

ACCEPTANCE TESTS OF SOFTWARE AND HARDWARE COMPLEX OF CONTROL AND MEASURING DEVICES OF THE NORMAL OPERATION SYSTEM FOR THE TURBINE DIVISION CARRIED OUT

03.12.2022

ACCEPTANCE TESTING OF RELAY PROTECTION AND AUTOMATION EQUIPMENT STARTING RESERVE TRANSFORMER AT SOUTH-UKRAINE NPP

19.11.2022

ACCEPTANCE TESTS OF SOFTWARE AND HARDWARE TOOLS FOR MODERNIZATION OF AUTOMATION SYSTEMS OF NPP POWER UNITS WERE CARRIED OUT

26.10.2022

THE INSTRUMENTATION AND CONTROL SYSTEM OF THE AUTOMATIC REGULATING SYSTEM OF THE REACTOR DIVISION NORMAL OPERATION SYSTEM IS INTRODUCED TO OPERATION AT KhNPP

07.10.2022

TYPE TESTING OF MICROPROCESSOR-BASED RELAY PROTECTION AND AUTOMATICS DEVICES ImPR1

07.10.2022

MODIFIED REGISTRATION AND DISPLAY DEVICES WERE INTRODUCED INTO COMMERCIALLY COMMISSIONED AS PART OF THE AKNP-I OF POWER UNIT No. 3 RNPP

06.10.2022

OF BORON CONCENTRATION MONITORING SYSTEM IS INTRODUCED TO TRIAL OPERATION AT KhNPP

01.09.2022

THE ELECTRICAL EQUIPMENT OF THE POWER SUPPLY SYSTEM OF THE CONTROL AND PROTECTION SYSTEM WAS INTRODUCED INTO COMMERCIALLY COMMISSIONED AT KHNPP POWER UNIT No. 1

29.08.2022

FACTORY ACCEPTANCE TESTING CARRIED OUT FOR TRACK CIRCUITS SYSTEM MRC-U

24.08.2022

CENTRALIZED TRAFFIC CONTROL SYSTEM HAS BEEN COMMISSIONED AT «POMICHNA — CHORNOLISKA» SECTION