In accordance with the technical decision of ZNPP, in September 2016, the trial commissioning of the instrumentation and control system of the turbine regulating system (I&C of SRT) took place at Unit 1.
This was preceded by the following:
- receipt of permission for building and assembly, commissioning and adjustment;
- installation as to connection of external communications of I&C of SRT;
- metrological certification of measuring channels of I&C of SRT;
- preliminary test (autonomous and complex) of I&C of SRT;
- introduction of changes into maintenance documentation and development of new documentation after introduction of I&C of SRT;
- training of personnel involved into operation of I&C of SRT and knowledge assessment;
- development of a trial operation program for I&C of SRT at Unit 1.
Details