At unit 5 of Zaporizhzhya NPP from 5 to 9 November 2012 the acceptance testing of the SW & HW system of the normal operation system of the reactor division (manufactured by RPA “Impulse”), was carried out.
Based on the commission’s work results it was established that this equipment is ready for industrial commissioning at unit 5 of Zaporizhzhya NPP.