In May 2015, the instrumentation and control system of the normal operation system for the turbine division (I&C of NOCS for TO) to the extent of the control and measurement instrumentation (KIP) subsystem was put into commercial operation at ZNPP-2.

During the outage, the following was performed by personnel of the thermal instrumentation & control shop, PJSC “EYuM-10”, PJSC “SRPA “Impulse” and “Microdata” Ltd.:

  • dismantling of KIP equipment of NOCS for TO;
  • dismantling of equipment of the generator monitoring and diagnostics system;
  • dismantling of “Sapphir” measuring transducers;
  • installation of equipment of I&C of NOCS for TO;
  • installation of “Saphir” pressure sensors;
  • installation, check and connection of control cables and power cables for NOCS for TO;
  • laying and connection of a fiber-optic cable;
  • autonomous check of I&C of NOCS for TO;
  • complex debugging of dataware for information input and processing functions from I&C of NOCS for TO to the upper level of the control computer system;
  • check of measuring channels of I&C of NOCS for TO;
  • metrological certification of measuring channels of I&C of NOCS for TO;
  • acceptance testing of equipment of I&C of NOCS for TO (to the extent of the KIP subsystem);
  • unplanned instruction of operating personnel.

The specialized sub-commission has taken a positive decision on putting I&C of NOCS for TO to the extent of KIP for TO into commercial operation at unit №2 without remarks.