In February 2021, the instrumentation and control systems of the normal operation systems for the reactor and turbine divisions (I&C of NOS TO and RO) have been put into trial operation at unit 2 of KhNPP.
I&C of NOS TO and RO are designated to implement functions of receipt, normalization, and processing of input signals from primary measuring transducers, shaping of output current and discrete signals of the safety-related normal operation systems of the reactor and turbine divisions.
Based on the results of the testing, the commission stated that I&C of NOS TO and RO submitted for the testing meet the design, technological, operational, programme documents, the requirements of the terms of reference completely and is ready for commercial commissioning at unit 2 of KhNPP.