At power unit no.4 of Rivne NPP and power unit no.2 of Khmelnytska NPP systems for control of emergency “Coolant leak from the first circuit to the second with the equivalent section Dy 100” (SCE LFCS) have been put into operation in the telemetering mode.
...At power unit no.1 of Rivne NPP computer information system of upper block level (CIS) has been put into trial and commercial operation.
...The hardware and software of the process information system for the full-scale simulator of the training centre have been supplied to unit 1 of Rivne NPP.
...The SSA-4/3, SSA-4/5 smooth start-up automates have been shipped for units 3,4 of Zaporizhzhya NPP.
...On the 23-25th of September, 2009 in the International Exhibition Centre (Kiev) the seventh International Forum “Fuel and Energy Complex of Ukraine: the Present and the Future” took place.
...