On 9-10 November the acceptance testing of the modified software for instrumentation and control system of the accident and post-accident monitoring system (PAMS) for units 3, 4 of Rivne NPP was carried out at the site of SRPA “Impulse”.
...On 10-11 August the final stage of the acceptance testing of vibration monitoring and diagnostics system for reactor coolant pumps (VMDS RCP) for Unit 6 of Kozloduy NPP was carried out at the site of SRPA “Impulse”.
...On 14-16 July the acceptance testing of eight standby diesel generator station automatic control systems (SDGS ACS) for Units 1, 3, and 4 of Zaporizhzhya NPP was carried out at the site of SRPA “Impulse”.
...In May 2020, the acceptance testing of the instrumentation and control system of the safety control system of WWER-1000 (ESFAS-2 I&C system) for Unit 5 of Zaporizhzhya NPP was carried out at the site of PJSC “SRPA “Impu...
From 10 to 12 March the handover-acceptance testing of the boron concentration monitoring system based on NAR-I and NAR-I2 neutron solution analyzers for unit № 5 of Zaporizhzhya NPP was carried out at the site of SRPA “Impulse”.
...